分条机的安全操作步骤

2023-04-25 16:35:09

1、送电。合上控制柜内空气开关,分条机电源指示灯亮,注意手指不能碰到接线端子,小心触电,危及安全。
1. Power transmission. Close the air switch in the control cabinet, the power indicator light of the stripper will be on, pay attention not to touch the terminal with fingers, be careful of electric shock, which may endanger safety.
2、上帘布卷。打开导开安全卡头,吊上帘布卷,合上安全卡头,分离帘布和胶布,把帘布缠绕到收卷布筒上。
橡胶托辊 槽型托辊 皮带托辊 平行托辊 保定搬家 保定搬家电话 保定搬家公司 保定搬家 铜鼎 铜狮子
2. Upper cord roll. Open and open the safety clip, hang up the cord fabric reel, close the safety clip, separate the cord fabric and the adhesive tape, and wind the cord fabric onto the take-up drum.
3、人工传胶布。导开打到手动,正转点动导开 ,人工拖着胶布,穿过纠偏辊,张紧辊,刹车辊,驱动辊。
3. Manual tape transfer. Turn the guide to manual, turn forward and move the guide, manually drag the adhesive tape, pass through the correction roll, tension roll, brake roll and drive roll.
4、抽线。根据要生产胶条尺寸用剪刀剪开胶条,然后抽线,并固定在抽线辊上。
4. Draw line. According to the size of the rubber strip to be produced, use scissors to cut the rubber strip, then draw and fix it on the drawing roller.
5、上卷曲辊。卸下卷取轴头端方轴,装上30个尼龙卷轴,再装上方轴,打开卷取安全卡头,装上卷取轴,卷取1和卷取2操作一样。
5. Upper winding roller. Remove the square shaft at the end of the coiling shaft head, install 30 nylon reels, then install the upper shaft, open the coiling safety clip, and install the coiling shaft. Coiling 1 and coiling 2 operate the same.
6、上胶布头。把胶条拉伸到合适位置,把胶条缠绕到卷轴上,注意胶条长度要保持一致,来保持胶条张力一致。
6. Glue the cloth head. Stretch the adhesive tape to the right position, wind the adhesive tape on the reel, and pay attention to the consistent length of the adhesive tape to keep the consistent tension of the adhesive tape.
7、调节张力。调节卷取张力到6.5-10之间,把导开张力调节到10-15之间,注意随着卷取直径加大,卷曲张力适当增加,保证胶条张力一致。
7. Adjust the tension. Adjust the coiling tension to 6.5-10, and the guide tension to 10-15. Pay attention to the appropriate increase of coiling tension with the increase of coiling diameter to ensure the consistent strip tension.
8、调节卷取速度。调节卷取速度在需要范围内,注意启动时卷取速度不能太大,以免纠偏跟踪错误,可以调节到20启动后再增速。
8. Adjust the coiling speed. Adjust the coiling speed within the required range. Pay attention to that the coiling speed should not be too large when starting, so as to avoid deviation correction and tracking error. The coiling speed can be adjusted to 20 and then increased after starting.
9、启动机器。上述操作完成后,按启动按钮,转动一两圈后,观察卷轴胶条是否有偏移不正状态,若有,停止卷取,摆正位置,再继续旋转。同时注意抽线线头位置,来调节抽线启停,防止线头拉断或夹线。
9. Start the machine. After the above operation is completed, press the start button and rotate it for one or two circles to observe whether the rubber strip of the reel is deviated. If so, stop coiling, put it in the right position, and then continue to rotate. At the same time, pay attention to 